As an expediter, I need to acknowledge the agreement and establish contact with a representative of the supplier.
-
As an expediter, I need to verify and plan the expediting events, defining critical and recurring events that will allow the system to automatically warn the expediter of upcoming critical steps and actions.
-
As an expediter, I need to define the baseline for supplier progress.
-
As an expediter, I need to issue a request for information to the supplier; for example, the manufacturing plan, quality control plan, VDRs, and so forth.
-
As a supplier, I need to provide or update the information requested by the expediter. This information might include sub-orders.
-
As an expediter, I need to distribute the information received from the supplier to the project stakeholders. Some of this information will be distributed automatically; other information must be distributed manually.
-
As an expediter, I need to adjust the line item shipments, and update other information such as the forecast delivery dates, delivery places, routing method, and so forth.
-
As an expediter, I need to report the material status to the project stakeholders.