To view the Change Details by Change report, perform any of the following actions.

  • View the report in the Changes screen:

    1. Navigate to Changes > Changes.

    2. Click the Reports tab.

    3. Click the Change Details by Change hyperlink. A dialog box appears with a title Change Details by Change.

    4. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    5. Click the Run button. The preview of the report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Changes > Change Details by Change.

    2. Click the Project ellipsis to select the required project. By default, the last selected project appears.

    3. Click the Run button. The preview of the report appears.