View the Project Structure and its Schedule - EcoSys - 2.03 - Help - Hexagon PPM

EcoSys Help - Projects (2.03)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
2.03

This procedure allows you to view the project structure along with its existing schedule.

  1. Navigate to Projects > Project Schedule.

  2. At the top of the screen, in the green parameter bar, click the Project and Calendar ellipsis to select the required project and calendar.

    The administrator defines calendars which include the time-zone, start time, duration, working days, and non-working days.

  3. Click Refresh for screen update. In the Project Scheduler panel, the project structure appears and the tasks along with their dependencies appear on the gantt chart.

    You can filter the object rows by entering their name in the Filter box.

  4. Click the Upper Arrow icon in the Object column to view the correct sequence of the object rows in the Project Scheduler panel.

  5. On the gantt chart, select the required timescale from the Timescale Unit list to view the tasks and milestones based on a timescale. The available options are listed below:

    • Year

    • Quarter

    • Month

    • Week

    • Day

  6. On the gantt chart, click the Show subscale check box and select the required timescale from the Timescale Subunit list to view the tasks and milestones based on a timescale. The available options are listed below:

    • Year

    • Quarter

    • Month

    • Week

      The Timescale Subunit scale should logically coincide with the Timescale Unit. For example, if you select the Timescale Unit as Year, then select Timescale Subunit as Day.