This procedure allows you to add or remove a project from a portfolio.

Projects should be assigned to standalone portfolios or portfolios at the bottom of the portfolio hierarchy. They should not be added to parent portfolios.

  1. Navigate to Portfolios > Assignments.

  2. In Project Selection Register panel, do any of the following:

    • Click the Add hyperlink. This adds the selected project to the portfolio.

    • Click the Remove hyperlink. This removes the selected project from the portfolio.

  3. Click the Refresh button to view the updated project data in the bar charts.