After creating the first revision (revision 0) of a specification in Smart Reference Data, you issue the specification and then revise it.
Make sure that all idents are generated for all the specification items before you issue the specification.
-
Go to SRD > Spec > Spec Management.
-
Click Edit Grid.
-
Check Issue for a specification, right-click and select Revise.
-
Now there are two specs shown, one with Rev 0 and one with Rev 1. Rev 1 is circled in the picture below.