  1. In the Domain Explorer, expand the Panels by Category folder and then the DCS Panels folder.

  2. Right-click 101-DCS-001, then on the shortcut menu, click Actions > I/O Assignment.

    If the I/O Assignment Type dialog box opens, select the I/O assignment option and click OK.

  3. Make sure that in the Assignment details pane, under I/O termination, the software displays 101-DCS-001, File Number 1, 1, 8 CH AI.

  4. On the module toolbar, click to open the I/O Assignment Filter dialog box, define the filter as follows:
    In the Filter for section:

    • Check, Unassigned instruments coupled with control system tags

    • Check, Uncoupled control system tags

    • Check, Uncoupled instruments

  5. Click OK

  6. In the Tag list pane of the I/O Assignment window, from the Sort by list, select Tag number to sort the display of tags in the pane.

    The I/O Assignment window should now appear as shown:

  7. Select tag 101-FT-100 and drag it from the Tag list to Channel 1 in the Assignment details pane.

  8. On the Control System Tag Properties dialog box, click in the Control system tag box, and change the name of the control system tag to BFI 100.

  9. Click OK to return to the I/O Assignment window.

    The I/O assignment of tag 101-FT-100 appears as shown:

  10. Repeat the above steps to do the following:

    1. Select tag 101-FT-102, assign it to channel 2, and name its coupled control system tag BFI 102.

    2. Select Tag 101-PT-201, assign it to channel 7, and name its coupled control system tag BPI 201.

      The assignments should now appear as follows: