Control Site - Level 1 - Intergraph Smart Materials - Version 2.0 - Reference - Hexagon

Intergraph Smart Materials Enterprise Work Process for Materials Management

Language
English
Product
Intergraph Smart Materials
Search by Category
Reference
Smart Materials/Smart Reference Data Version
2020 (10.0)
  1. As a construction planner, I need to define the material work packages and their priorities.

  2. As a member of the material controls team, I will provide the status of materials.

  3. As a construction planner, I need to simulate materials availability for allocation, adjusting the priorities and the material as necessary and interacting with the material controls team to expedite material availability.

  4. As a construction planner, I need to allocate the required materials.

    See the work process Allocate Materials - Level 2 Diagram for more information.

  5. As a material receiver, I need to receive the materials. If the materials have not been received in good order, I will initiate an over/short/damage process.

  6. As a warehouse manager, I manage the inventory of the stored materials and am responsible for all transactions related to materials in the warehouse.

  7. As a warehouse manager, I need to transfer and issue the required materials.

  8. As a member of the subcontractor/crew, I will receive the material and fabricate and/or install materials.

    See the work process Manage, Fabricate, and Install Materials - Level 2 Diagram for more information.