Regenerate the Reports database - Intergraph Smart 3D - Administration

Intergraph Smart 3D Project Management

PPMProduct
Intergraph Smart 3D
PPMCategory_custom
Administration & Configuration
Version_SThreeD_Custom
10.1 (2014 R1)

Before starting this procedure, check with your administrator to verify that all users are disconnected from the database.

  1. Select a model database in the Project Management tree view.

  2. Click Edit > Regenerate Reports Database.

    The Regenerate Reports Database dialog box displays.

  3. Review and, if necessary, edit the information displayed for the reports databases and servers.

  4. Click OK to regenerate the reports database.

  • Reports databases must have unique names. If the reports database name you specify is identical to one that already exists, you are prompted to either rename the database or reuse the existing reports database.

  • If the software is unable to successfully create the reports schema, an error message displays and the process ends.