Create or Update P6 WBS to EcoSys - EcoSys - 1.1 - Help - Hexagon PPM

Integrating EcoSys with P6 Connector

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Version
1.1

This job assumes that the EcoSys Cost Object structure is imported from P6 as a 1:1 relationship. It performs the following functions:

  • Update the EcoSys Project record

  • Create or Update P6 WBS to EcoSys Cost Objects

The P6 WBS and EcoSys Cost Object are mapped by assigning the P6 Object Id to the EcoSys WBS Cost Object External Key field.

  • Connect Job: P6 Project and WBS Import

  • EcoSys Action: ITG P6 Project WBS Import

Field Mappings

The following table shows the field mapping for the Project update part of the job:

EcoSys Field

EcoSys Subject Area

P6 Field

Cost Object ID

Cost Object

N/A

Cost Object Name

Cost Object

Project Name

P6 Project Status (ID)

Cost Object Category

Project Status

P6 Project (ID)

Cost Object Category

Project Id

P6 Object Id

Custom Field (Text)

Project Object Id

The following table shows the field mapping for the WBS create/update part of the job:

EcoSys Field

EcoSys Subject Area

P6 Field

Cost Object ID

Cost Object

WBS Code

Cost Object Name

Cost Object

WBS Name

Hierarchy Path ID

Cost Object

Calculated based on the WBS parent/child relationship

External Key

Cost Object

WBS Object Id