On the Milestone Planning tab, you can perform all the tasks that are related to the tracking of milestone dates for the selected planned requisition.

For more information, see Milestone Planning in the Tagged Items Planning section above.

If you have set up a milestone plan for a requisition supplement, the Supplement drop-down list appears at the top of the Milestone Planning tab, together with the associated ROS Date, Lead Time, and Planned Issue fields. If a requisition is linked to the planning supplement, the minimum ROS date of the requisition line items is displayed in the ROS Date field and cannot be changed.

Select a requisition supplement from the drop-down list to display the corresponding milestone plan.

You can right-click in the Supplement box to open a shortcut menu, which provides the Refresh supplement plan option. This functionality allows you to easily add to the selected supplement plan all milestone labels that are part of the milestone set assigned to the associated planned requisition, but that are not currently contained in the selected supplement plan. Using this option is more convenient than adding the milestone labels manually one by one.

The Orig. MH field displays the manhours defined on P.10.62 for the milestone.

In the MH field, you can enter the actual manhours.

In the % Progress field, you can enter the actual progress of the milestone.

Click the Suppl. Attrs button to open A.50.21 Attached Attributes, where you can attach attributes to the supplement plan. This button is only enabled for supplement plans.

Click the Attributes button to open A.50.21 Attached Attributes, where you can attach attributes to the selected milestone. For more information, see Attached Attributes.