The Time-Phasing tab provides access to all change line items. It displays values across a range of time periods rather than a single total of values. If the Manual curve type has been selected for the applicable change, period values can be directly edited.

  1. Navigate to Changes > Contract Changes.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.

  3. If required, click REFRESH to update the screen.

  4. Click the Contract Change Register tab.

  5. Click the Contract Change ID hyperlink. The Contract Change Details panel appears.

  6. Click the Time-Phasing tab.

  7. Select the Start Period and End Period to update the time-phasing data of the selected period.

  8. Type in the estimated Quantity of resources for the required year and month.

    For example, if the quantity for the year 2019 and the month January must be estimated, type the value in the Jan 2019 Quantity column.

  9. Type in the estimated number of Hours for the required year and month.

    For example, if the hours for year 2019 and the month January must be estimated, type the value in the Jan 2019 Hours column.

  10. Type the estimated number of Cost for the required year and month.

    For example, if the cost for the year 2019 and the month January must be estimated, type the value in the Jan 2019 Hours column.

  11. Click SAVE.

  12. If required, click REFRESH to view summary updates.