The Manual Factor amount can be updated manually for contract lines with a Manual Factor forecasting method.

  1. Navigate to Forecasts > Contract Forecast.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.

  3. Click Refresh for screen update.

  4. Click the Contract Forecast tab.

  5. Type the Manual Factor for the contract lines with Manual Factor forecast method.

  6. Click the Save icon.

    Manual Factor forecast method calculates the New EAC value using the formula: [AC + ((BAC-EV)/Manual Factor)]. Where AC is actual cost, BAC is Budget at Completion value, and EV is earned value.