Contract Change Status Dashboard - EcoSys - 2.03 - Help - Hexagon PPM

EcoSys Help - Contracts (2.03)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
2.03

The Contract Change Status Dashboard provides the ability to view the contract change data by contract. The bottom panel is a graphical display of the contract change data listed in the top panel, which includes Change Name, Type, Status, Hours, and Costs.

To view the Contract Change Status Dashboard, follow the procedure below.

  1. Navigate to Changes > Contract Change Status.

    Or

    Navigate to Reports > Contract Change Status.

  2. At the top of the screen, in the green parameter bar, click the Project ellipsis to select the required project.

  3. If required, click REFRESH to update the screen.

    The Contract Change Register spreadsheet appears in the upper panel, the Changes by ID bar chart displays in the left lower panel, and the Changes by ID pie chart displays in the right lower panel.

  4. Click the Type hyperlink for a contract change in the upper panel. The Changes by Type panel appears.

  5. Click the Status hyperlink for a contract change in the upper panel. The Changes by Status panel appears.

  6. Click the Cost hyperlink for a contract change in the upper panel. The Change Details panel appears.