This procedure allows you to update the Manual EAC amount manually for contract lines with a Manual EAC forecasting method.
-
Navigate to Forecasts > Contract Forecast.
-
At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.
-
Click Refresh for screen update.
-
Click the Contract Forecast tab.
-
Type the Manual EAC for the cost control objects with Manual EAC forecast method.
-
Click the Save icon.