Review Schedule - PDS - Help

Plant Design System (PDS) Interference Checker/Manager (PD_Clash)

PPMProductFamily
3D Design and Visualization
PPMProduct
PDS
PPMCategory
Help

The Review Schedule option lists all scheduled envelope/clash jobs for the active project and displays the following basic data.

  • archival number

  • frequency of build/check

  • time of day for build/check

  • network address for build/check

  1. Select Option.

    Select the Review Schedule option from the Scheduled Build Envelope/Clash Detection form.

    The Review Envelope Build/Clash Detection Schedule form is displayed.

  2. Cancel Review Schedule.

    Choose the Cancel button to display the Scheduled Build Envelope/Clash Detection form.