MTO Type - Intergraph Smart Materials - Version 2016 R4 (8.4.0) - Help - Hexagon PPM

Intergraph Smart Materials Classic Help (2016)

PPMProduct
Intergraph Smart Materials
PPMCategory_custom
Help
Version_SPMat
2016 R4 (8.4)

The MTO type describes all characteristics of an MTO: the structure of the resulting engineering requisitions, and the criteria for the material selection and quantity calculation.

  1. Open the R.10.51 MTO Types screen.

  2. Enter the type name in the Type box.

  3. Select Standard from the MTO Option list.

  4. Select the Ident check box.

  5. Select No from the Tag Option list.

  6. Select the MTO Crit check box.

  7. Select the pre-defined BOM set in the BOM Set box.

  8. Select the pre-defined requisition node in the Req Node box.

  9. Select the pre-defined requisition split criteria in the Req Split box.

  10. Select the pre-defined disposition rule set in the Dispo Rule Set box.

  11. Click Save.

  12. Click the Group By button to open Window 2.

  13. Type a number in the Order Seq box.

  14. Select X-DIM from the list in the Attribute box.

  15. Do the same for the Y-DIM attribute.

  16. Click Save.