Complete the requirement - Intergraph Smart Construction - 2019 (7.0) - Help - Hexagon PPM

Managing Constraints from Smart Construction in the Web Client (2019)

PPMProduct
Intergraph Smart Construction
PPMCategory_custom
Help
SPCVersion_custom
2019(7.0)
SPFVersion_custom
10

When the request is fulfilled, you set the Status to Completed.

  1. Show your list of constraint requests.

  2. Select the constraint you're scheduling and select Actions > Update.

  3. Change the Status to Completed.

  4. Select Update to save the change.

Unless you set the Completed Date yourself to something else, the current date will be used when you save the change.