Complete the requirement - Intergraph Smart Construction - 2019 (7.0) - Help - Hexagon PPM

Managing Constraints from Smart Construction in the Web Client (2019)

Language
English
Product
Intergraph Smart Construction
Search by Category
Help
Smart Construction Version
2019(7.0)
SmartPlant Foundation / SDx Version
10

When the request is fulfilled, you set the Status to Completed.

  1. Show your list of constraint requests.

  2. Select the constraint you're scheduling and select Actions > Update.

  3. Change the Status to Completed.

  4. Select Update to save the change.

Unless you set the Completed Date yourself to something else, the current date will be used when you save the change.