On the Schedule of Values tab, you can create your own SOV items.
You can click Copy from to create a copy of an existing SOV item.
-
Click Contract Scope - Schedule of Values on the menu.
-
Click Add Price Breakdown .
-
Type a unique name in the Item Code box.
-
Type the item description in the Description box.
-
If required, select an account code from the list in the Account Code box.
-
If required, select an activity code from the list in the Activity Code box.
-
Enter values in the Material Total, Construction Equipment Total, Consumables Total, and Others Total boxes.
-
To define the labor costs, click Details in the Labor Hours box and do the following:
-
Click Add .
-
Type a sequence number in the Seq cell.
-
Click Labor Classification and select a rate type.
-
Type the estimated number of labor hours in the Hours cell.
-
Type the hourly rate in the Unit Rate cell.
-
The total is calculated by multiplying the hours with the unit rate and displayed in the Total cell. This value cannot be changed.
-
The currency is populated from the price breakdown and cannot be changed.
-
-
Click Save.
-
Click Price Breakdown > to return to the price breakdown overview.
-
-
If required, select a value from the Currency list to change the currency.
-
Click Save.
-
The Labor Total shows the sum of the labor detail totals.
-
The Overall Total field shows the sum of material total, labor total, construction equipment total, consumables total, and others total.