Auto-Association Dialog Box - Intergraph Smart Review - Help

Intergraph Smart Review Help

Language
English
Product
Intergraph Smart Review
Search by Category
Help
SmartPlant Foundation / SDx Version
7.1 (2018 R1)
Smart Review Version
13.x(2018)

Compares the names of existing groups to the names of existing tasks, and automatically associates the tasks with a group.

Match whole string

Looks for task names that exactly match the group name. For example, if you have a task named steel pipe, the task is only associated with a group called steel pipe.

Match substring of task name

Looks for task names with a substring that matches a group name. For example, if you have a task named paint steel pipe, the task can be associated with a group called steel pipe.

Match substring of group name

Looks for tasks that match a substring of a group name. For example, if you have a task called steel pipe, the task can be associated with a group called steel pipe iso15.

Match case

Matches tasks with groups using case- sensitivity. For example, Steel Pipe matches Steel Pipe, but not steel pipe. You can use this option in association with any of the three association methods.

Cumulative

Adds the result of the current operation to the existing set of associations. If not selected, ScheduleReview deletes associations before creating new ones. The Cumulative option also looks for task names with a substring that matches a group name. For example, if you have a task named paint steel pipe, the task can be associated with a group called steel pipe. You can use this option in association with any of the three association methods.

Match activity ID instead of task name

Associates tasks with display sets (groups) using the task activity name rather than the task name. For example, in the sample SPRDemo project and the ScheduleReview EXAM planner project (using Primavera), if you create a new display set named A00003 using the definition FIND Data Sequence = Major Equipment Foundation, then click Tools > ScheduleReview > Auto-Association and check the Cumulative option (so as not to delete any current associations) and the Match activity ID instead of task name option, the Accumulator Foundation task will be associated with the A00003 display set because it's Task Activity ID is A00003.

See Also

Create a New ScheduleReview Query
Add a ScheduleReview Association