Remove delay and update To-Do List records for internal structure - Intergraph Smart 3D - Help

Intergraph Smart 3D Molded Forms

PPMProduct
Intergraph Smart 3D
PPMCategory_custom
Help
Version_SThreeD_Custom
10.1 (2014 R1)
  1. Click Tools > Delay Settings.

    The Delay Operations dialog box appears.

  2. On the Delay Settings tab, click No Delay, and then click Apply.

  3. On the Update To Do Records tab, select Optimal.

  4. Select Out-of-Date Molded Forms. Clear all other Type options.

  5. For Structure to Update, select All.

    The number of delayed objects to update is shown in the Update To Do Records frame.

  6. Select Enable Logging.

  7. Click Update Objects.

    Updates of remaining delay records on the To Do List are performed by the software. For more information, see Optimal Update Processing for Hull Swaps.

  8. Click View Log File and check results of the update.

  9. Click OK.

For more information, see Delay Settings (Tools Menu) and Delay Operations Dialog Box.