The CLOSED requisition status is set when:
-
The requisition is created.
-
The requisition is approved.
-
The requisition is released to Procurement.
-
-
Which steps are needed to release a requisition to procurement when advanced approval is activated (project default ZR_ADV_APR is set to Y)?
-
Click the Release button to approve and release the requisition in one step.
-
Select the Ready for Approval check box.
-
Click the Approve button to approve the requisition.
-
Click the Release button to release the requisition to procurement.
-
-
Which quantity field can be updated on requisition line items created by an MTO job?
-
New List Quantity
-
Released Quantity
-
Increased Quantity
-
Recommended Quantity.
-
-
Which values are increased when a requisition supplement is created with quantity changes?
-
Supplement
-
MR Revision
-
SR Revision.
-
-
Which material can be found in the PIPING LEFTOVERS requisition used in this tutorial?