Define Delivery Requirements - Intergraph Smart Materials - Version 2020 (10.0) - Training - Hexagon

Intergraph Smart Materials Classic Lab Tutorials (2020)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Training
Smart Materials/Smart Reference Data Version
2020 (10.0)
  1. Open the R.30.01 Maintain Requisitions screen from the E&PI (Req) > R.30 Requisitions menu branch.

  2. Click the Run Query button to display the existing requisitions.

  3. Select the PIPING-FO FITTINGS requisition, and double-click in the Engineering Requisition field. Window 2 opens where the requisition line items are displayed.

  4. Use the scrollbar under the requisition line items to scroll to the right until the ROS Date fields are displayed.

    You can use the in the upper right corner to enlarge the screen.

  5. Select a date from the LOV in the ROS Date field, and click OK to insert the date and to close the LOV.

  6. Right-click in the ROS Date field to open the shortcut menu.

  7. Select the Populate downwards command from the menu. The software copies the date to all requisition line items below.

  8. Scroll further to the right to the Delivery Designation field.

  9. Click the List of Values button and select a pre-defined delivery designation from the LOV. Click OK to copy the value and to close the LOV.

  10. Right-click in the Delivery Designation field to open the shortcut menu.

  11. Select the Populate downwards command from the menu. The software copies the value to all requisition line items below.

  12. Save the changes using the Save button.

  13. Update the ROS Date and Delivery Designation values for the other requisitions in the same way.

  14. Close the screen by selecting File > Close All or Close from the main menu.