Purpose
This section explains how to assign other costs to the quote details.
Exercise
-
On the Quote Details tab on P.30.27 Bidder Quotation, double-click in the Seq field of the first quote detail.
Window 2 opens. The quote detail other costs are maintained on the Other Costs tab.
-
Select CERT from the LOV in the Other Costs field.
-
Enter 30 in the Cost Value Total field.
-
Click the New Record button to create a new record
-
Select TRANSPORT from the LOV in the Other Costs field.
-
Enter 5 in the Other Cost % field.
The cost value total is calculated and displayed in the Cost Value Total field.
-
Save the changes using the Save button.
-
Close Window 2 by selecting File > Close from the main menu.
-
Define quote detail other costs for the other quote details in the same way.
-
Scroll to the right to display the other costs fields.
The Gross Other Costs field shows the total of other costs without a discount, and the Net Other Costs field shows the total of other costs with discounts.
The quote detail net price is calculated as the discounted price + net other costs and displayed in the Net Price field.