Who can create inquiries based on requisitions?
-
Any user with access permissions to the P.30.01 screen.
-
The MSCM super user with the ASSIGN BUYER privilege.
-
Any user with the BUYER privilege.
-
The user who is assigned as the buyer to the requisition.
-
-
What has to be done before you can approve the inquiry if the project default ZP_SUPAPRV is set to Y?
-
Which of these prerequisites must be fulfilled before you can approve an inquiry?
-
At least one bidder must be assigned to the inquiry.
-
At least one other cost must be assigned to the inquiry.
-
At least one requisition must be assigned to the inquiry.
-
The revised bid due date must be set.
-
-
How can you restrict the list of available bidders to be assigned to the inquiry?
-
Commercial evaluation checklists are defined and used to …
-
technically evaluate and accept the quotes from the bidders
-
evaluate the commercial bids from the bidders
-
check if all prerequisites for the inquiry approval are fulfilled
-