Assigned Work Packages - Intergraph Smart Materials - Version 2020 (10.0) - Training - Hexagon

Intergraph Smart Materials Classic Lab Tutorials (2020)

Language
English
Product
Intergraph Smart Materials
Subproduct
Classic
Search by Category
Training
Smart Materials/Smart Reference Data Version
2020 (10.0)

Work packages are defined on C.10.05 as described in Work Packages in the Setup section.

Use the Fastcall to open the C.30.01.02 Assigned Work Packages screen.

To assign a work package in the second block, enter a sequence number in the Priority field, and select a pre-defined work package from the LOV in the Work Package field. The other fields in the second block and the list nodes in the third block are populated automatically from the work package. For the description of the fields, see Work Packages in the Setup section.

The priority determines the order of processing the work packages by the FR.

When an end date is defined for a work package that is assigned to the forecast run, this end date is used during the forecast instead of the end date specified for the forecast run in the Shipment Options section on C.30.01 Forecast Run.