Purpose
This section explains how to define a forecast run to simulate materials availability.
Exercise
-
Open the C.30.01 Forecast Run screen from the Smart Materials > Site > Field Material Control > C.30 Construction Planning menu branch.
-
Click Cancel Query to switch to new record mode.
-
Enter FR-TRAIN01 in the Forecast Code field.
-
Enter FR-Training1 in the Short Desc and Description fields.
-
Select the status 0 from the LOV in the List Status field.
-
Save the changes using the Save button.
-
Open the Fastcall menu in the upper right corner.
-
Select C.30.01.01 Assigned Warehouses from the menu.
-
Enter 1 in the Seq field.
-
Select STORE from the LOV in the Warehouse field.
-
Save the changes using the Save button.
-
Close the screen.
You return to C.30.01.
-
Open the Fastcall menu in the upper right corner.
-
Select C.30.01.02 Assigned Work Packages from the menu.
-
Enter 1 in the Priority field.
-
Select the pre-defined WP-PIPING from the LOV in the Work Package field.
-
Save the changes using the Save button.
The BOM list nodes assigned to the selected work packages appear in the lower block.
-
Close the screen.
You return to C.30.01.