To load the SPO Project Execution solution, complete the following steps:
-
Open the SmartPlant Foundation Desktop Client.
To load the Schema and Admin files there is no need to set the scope
-
Click File > Loader to open the Loader.
-
Navigate to the installation path SPX\Project Execution\STs\SmartPlant Project Execution (SPO_ProjExec) and select 001 - SPOPE_SCHEMA_ALL.xmlldrs.
-
Click Process and wait until the loading is finished.
The green color indicates the process is finished successfully.
-
Repeat the above steps to load the following file: 002 - SPOPE_ADMIN_ALL.xmlldrs.
-
Close the Loader dialog box.
To load the Data and Workflow files please set the scope to the required plant [plant A] and click OK.
-
Click File > Loader to open the Loader.
-
Navigate to the installation path SPX\Project Execution\STs\SmartPlant Project Execution (SPO_ProjExec) and select 003 - SPOPE_DATA_ALL.xmlldrs.
-
Follow the above steps (4 and 5) to load the following file: 003 - SPOPE_DATA_ALL.xmlldr & 004 - SPOPE_WORKFLOW_ALL.xmlldrs.
-
Close the Desktop Client.
-
Reset the IIS (Start > Run > iisreset) and reopen SmartPlant Foundation Desktop Client.