With this project default, you can control whether it is allowed to define other costs as discounts or not.
If the project default is set to Y (default), you can define other costs as discounts. This means that you can enter a negative value in field OC Percent.
If the project default is set to N, you cannot enter negative values in this field. In other words, you cannot define discounts on the other cost level.
This project default is used by screens P.30.22, P.30.27 and P.50.07, and in Smart Materials Portal.
-
Module(s) affected by this setting: P3022, P3027, P5007, Smart Materials Portal
-
Default value: Y
-
Available values: N/Y