Assign planned tags to planned requisitions - Intergraph Smart Materials - Version 2016 R4 (8.4.0) - Help - Hexagon PPM

Intergraph Smart Materials Help (2016 R4)

PPMProduct
Intergraph Smart Materials
PPMCategory_custom
Help
Version_SPMat_custom
2016 R4 (8.4)
  1. Click the Planning task on the dashboard, or select Planning from the Tasks list.

  2. Select a planned tag in the tree.

    The planning item details appear on the right panel.

  3. Click Planning to display the Planning section.

  4. Select the Planned Requisitions tab.

  5. Click Add Engineering Requisition .

  6. Select the check box in the first column for all requisitions you want to assign to the selected planned tag.

  7. Click Add.

  8. Click Save.

To remove a requisition, select the record and click Delete .