Publish the schedule to Primavera P6 - HxGN Smart Build - Version 3.0 U4 (3.0.4) - Help - Hexagon PPM

HxGN Smart Build Help

PPMProduct
HxGN Smart Build
PPMCategory_custom
Help

Scenario: Your team members want to have a look at the updated schedule in Primavera P6 account of your project.You must now publish the schedule to be able to see the changes in Primavera P6.

  1. Click Schedule Management > Planning .

  2. Click options > Publish to P6.

    The application publishes the schedule and calendar related to the integrated project in P6.