The ZI_MOB_RM project default allows a project to turn off one of the checks that is done to filter POs that are downloaded to the app. By default, any POs that do not have a routing method defined are not downloaded to the app for expediting (the default value being Y). Defining routing methods greatly improves the expediting process (automates updating of dates) so it is highly recommended to use them.

  1. Sign in to Smart Materials.

  2. Open the A.20.12 Project Defaults screen, select the Integrator tab and query for the ZI_MOB_RM project default.

  3. Type N in the Value box and save to turn off the filtering of POs that download to Mobile Companion.

    For more information about project defaults, see Smart Materials Project Defaults .