Plan requisition supplements - Intergraph Smart Materials - Version 10.1 - Help - Hexagon

Intergraph Smart Materials Help (10.1)

Language
English
Product
Intergraph Smart Materials
Subproduct
(WPF)
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.1

Requisition supplement planning is only available if project default ZP_MS_SUPP is set to Y or E. If the project default is set to E, the supplement planning is enforced, that means that at least one supplement plan must exist for each planned requisition.

  1. Click the Planning task on the dashboard, or select Planning from the Tasks list.

  2. Select a requisition planning item in the tree.

  3. Click Planning to display the Planning section.

  4. Select the Milestones tab.

  5. Click Add Supplement Plan Com_Add ICON to add a requisition supplement plan.

  6. Type the supplement number in the Suppl box.

  7. Select Purchase if the requisition should be used to create an agreement, or do not select the check box if the requisition is for inquiry only.

  8. Click ROS Date Com_DateAndTime ICON and select the date when the material is required on site.

    If a requisition is linked to the plan, the minimum ROS date of the requisition line items is displayed. This ROS date can only be changed, if project default ZP_MS_ROS is set to Y.

  9. Type a value in the Lead Time box.

    The lead time value is interpreted as weeks by default. This can be changed in the M_PCK_MS_CUSTOM.CALC_PLANNED_ISSUE_DATE CIP.

    The Planned Issue date is calculated as ROS Date - Lead Time, and this date cannot be changed.

  10. Click Save.

  11. Click the requisition number to edit the milestones (see Edit milestone planning).