In the event of the production server failing, the following steps are required to failover to the standby server:
-
Stop the production services if they are still running.
-
If backup and restore is used, ensure that the latest production backup is present on the standby server.
-
Start the services on the standby server.
-
Redirect users from using the production server to using the backup server, in one of the following ways:
-
Update the DNS entries so that the standard j5 URL direct users to the standby server.
-
Inform users to use the new standby server URL.
-