Determines how the section displays and handles submission. This feature can only be applied to sections (in other words, it cannot be applied to subsections).

The following options are available:

  • No Submit Button – The section doesn’t have a Submit button. The section is automatically submitted when the last section with a Submit button in the IndustraForm is submitted (this section is not necessarily the last section in the IndustraForm, but the last unsubmitted section with a Submit button). If there are incomplete required fields or invalid entries in earlier sections without a Submit button, the Submit button in the last unsubmitted section is grayed out.

  • No Revise Button – The section doesn’t have a Revise button when the section is submitted. In other words, the section can’t be revised after it has been submitted.

  • Require Signature – The section can only be submitted when a signature is captured. When the end user clicks the Submit button, a signature box appears. If the user cancels the signature box, the section still needs to be submitted.

  • Complete if – This feature is only editable when the No Submit Button check box is selected. This box allows you to set a condition for the section’s completion.

    When the Complete if condition refers to a Choice option or a Checklist Item with the Done label, the Choice option referred to in the Complete If condition and the Done button can't be selected/clicked when the section has an invalid value. These options are grayed out.

  • Enabled offline for mobile – The section can be submitted on j5 Mobile, even when the user’s mobile device is offline.

  • Enabled before "Start Handover" – This is only available for shift handover IndustraForm templates. In general, sections on a shift report can only be submitted after the shift handover process has begun. When this option is selected, the section (for example, a pre-shift planning section) can be submitted before the shift handover has started.