Construction Planning - Intergraph Smart Reference Data Standard Database - Version 12.2 - Help - Hexagon PPM

Standard Database for Intergraph Smart Reference Data Smart Material Workflows Help

Language
English
Product
Intergraph Smart Reference Data Standard Database
Search by Category
Help
Standard Database for Smart Reference Data Version
12.2

Forecast Run

Each forecast run is based on a forecast header which defines parameters like work packages / warehouses used etc. for this run. A forecast run does no reservations. After the forecast is run, the inventory will not be changed.

Forecast Run section on SDB is defined with sample forecast jobs with the following default options.

Run Options

Allocate Level

Only Inventory

All positions

True

Position with full site-qtys

True

BOM Options

Best Quantity

True

List Status

0

Following is the list of sample forecast jobs with different shortage run options.

Shortage Run Options

Sample Forecast Run Job

2-Pass Optimized (1)

SAMPLE_PIP_2PO_1

2-Pass Optimized (2)

SAMPLE_PIP_2PO_2

2-Pass Optimized (Any)

SAMPLE_PIP_2PO_ANY

Only Entire Drawing

SAMPLE_PIP_OED

1-Pass Single (Any)

SAMPLE_PIP_1PS_ANY

Reservation Run

Each Reservation run is based on a Reservation header which defines parameters like work packages / warehouses used etc. for this run. A reservation does real reservations against the inventory. This means, quantity of the inventory on hand and the expected quantity in BOM will be increased.

Sample Reservation "Piping_2, Run 1" is created and executed for Materials Issue workflows.