  1. In the Source zipped package field, select the RDS package created at the source plant.

  2. Specify the target plant into whose reference data you want to merge the package selected above as follows:

    1. Click the ellipsis button to navigate to the SmartPlantv4.ini file of the site that includes the relevant plant.

    2. From the Target plant name list, select the desired plant.

  3. Do one of the following:

    • Click File > Synchronize.

    • On the toolbar, click .

    • The File > Synchronize command is not enabled until the comparison process between the selected source package and target plant is successfully completed.

  4. View the synchronization results in the Status and results window.

  • A plant cannot be synchronized if the comparison process returned any items with errors.

  • If the synchronization fails, you must extract any original reference data files from the archive to undo the change.