When the request is fulfilled, you set the Status to Completed.
-
Select the constraint you're scheduling and select Actions > Update.
-
Change the Status to Completed.
-
Select Update to save the change.
Unless you set the Completed Date yourself to something else, the current date will be used when you save the change.