Edit data in Construction Lead Module - Intergraph Smart WQMS - 6 - Help - Hexagon PPM

Intergraph Smart Weld Quality Management System Help

Language
English
Product
Intergraph Smart WQMS
Search by Category
Help
Smart WQMS Version
6

In Construction Lead module, you can edit the properties of Welding and NDT modules.

While editing the properties in Construction Lead module, the date validations for Welding and NDT modules must not be modified.

  1. Click Construction Lead module.

  2. In the search bar, enter *, select any filter criteria, and click Refresh .

    The software displays all the ISO/Drawing Numbers that satisfy the filter criteria.

    If you want particular drawing numbers to be displayed in the ISO/Drawing No list:

    • Copy the ISO/Drawing numbers from the Excel sheet and paste them in the Search bar. After you paste the drawing numbers in the Search bar, they are separated with the | symbol.

      For example, If you copy two drawing numbers from the Excel sheet and paste them in the Search bar, the drawing numbers appear as as HXN81X-S91011-IS030015|HXN81X-S91011-IS030016 separated with the | symbol.

    • In the Search bar, type the ISO/Drawing number in the format below:

      *last two digits of the drawing number* or *Drawing number pattern*

      For example, if the drawing number is HXN81X-S91011-IS030015, in the Search bar, type *15* or type *S91011*. Then only the drawing numbers related to the pattern will be displayed in the ISO/Drawing No list.

      This is applicable to all the modules of Weld Quality Management System where ever there is a filter criteria for ISO/Drawing numbers.

  3. Select an ISO from the list, and all the welds on that ISO are displayed in the table.

  4. Select a weld. The following properties on the weld must be read only:

    • CWP No.

    • ISO No.

    • Revision

    • Thickness1

    • Thickness2

    • SPEC

    • Inch Dia

  5. Click on the weld and edit the date.

  6. Click OK.

  7. Select a weld and click Assign Welders . The assigned welders for the weld are displayed in ASSIGN MULTIPLE WELDERS box.

  8. Select the welder from the Selected Welders list and click left arrow to un-assign the assigned welder.

  9. Select the welder from Available Welders list and click right arrow to assign a new welder to the weld.

  10. Click Generate Weld Cardto generate a report for the weld data.