Visual Inspection is an inspection process performed to verify the integrity of the weld by conducting various Non Destructive Test (NDT) tests for the welds.

  1. Click the Visual Inspection module.

  2. Click Notice of Inspection.

  3. In Select Module list, select the required module.

  4. Click Create Notice of Inspection to create an NOI with the selected components.

  5. Select the NOI and click Manage Inspection Items .

    Only the components that were selected while creating the NOI appear in the Manage Inspection Items table.

  6. Enter the data for the required properties and click Save Inspection Items.

  7. Select the NOI and click Generate Notice of Inspection . The software generates the report for the selected NOI.

  8. Select a weld and the Assign Welders .

    The first two welds performed by a welder are set as production welds for a project in a discipline. By default, these production welds are sent to RTE inspection. To modify or configure the data related to production welds, refer to Configure the conditions for Production and Tracer welds.

  9. Click Report of Inspection.

  10. Click Create Report of Inspection from NOI . The Create Visual Inspection ROI dialog box appears.

  11. On the Main Details page, enter the following properties and click Next. The Select NOIs page appears.

    • Description

    • Module

    • Area

    • Unit

    • Block

    • Work Package

    • Requested By - By default, the login user.

      The NOIs that satisfy the criteria selected in the Main Details page appear.

  12. Select the required NOI/NOIs and click Finish. An ROI corresponding to the selected NOI/NOIs is created.

  13. Click Create Report of Inspection from drawings . The Create Piping VIS ROI dialog box appears.

  14. On the Main Details page, enter the following properties and click Next. The select drawings page appears.

    • Description

    • Module

    • Area

    • Unit

    • Block

    • Work Package

    • Requested By - By default, the login user.

  15. Select the required drawings and click Finish. The Select Inspection Items page appears.

    The welds related to the selected drawings appear. The weld components related to the welds must be accepted in Fit-up Verification stage.

  16. Select the required weld and click Finish. An ROI for the selected weld is created.

  17. Select the ROI and click Manage Inspection Items . The Manage Inspection Items table appears.

  18. Enter the properties and click Save Inspection Items.

    • To display the welds in NDT (BSR), PostWHT and NDT (ASR) modules, set the properties Is NDT Required, PostWHT and Is Post NDT Required to Y (Yes) and click Accept Item in Manage Inspection Items. Then, accept the welds in NDT (BSR) to display them in PostWHT. Similarly, accept the welds in PostWHT to display them in NDT (ASR).

    • If you set the weld properties Is NDT Required and PostWHT to Y (Yes) in Manage Inspection Items, but do not accept in NDT (BSR) module, then those welds are not visible in PostWHT module.

  19. Select a weld and click Accept Item . The Accept Item dialog box appears.

  20. Enter the following properties and click Save.

    • Inspector Name - By default, login user.

    • Inspection Date - By default, today’s date.

    • Accept reason

      The Fit-up Internal Result and the Fit-up Client Result are set to Accepted on the weld. The Accept reason and inspection date are set in the appropriate fields on the weld.

  21. Select a component and click Reject Item . The REPAIR ITEM dialog box appears.

  22. Enter the following properties and click Save.

    • Inspector Name - By default, login user.

    • Inspection Date - By default, today’s date.

    • Reason for Repair - The following cases occur:

      • Repair Segment: If you select the reason for repair as repair segment, a new weld segment is created with a suffix Rx (where x is the number of repair segments). A weld can be repaired thrice after which the weld is cut or disabled, and a new segment is created with a new weld label Cx.

        For example, if a weld W01 is rejected during visual inspection and Repair segment is selected as the reason for repair, a new weld segment is created as W01_R1 (where 1 is the first repair segment or the weld is rejected for the first time). If the newly created weld segment W01_R1 is also rejected, then another repair segment is created as W01_R2 ( Which means the weld is rejected for the send time). If the weld is rejected thrice, the weld is disabled, and a new weld segment is created with a new weld label W01_C1.

      • Re-weld: If you select the reason for repair as re-weld, then the original weld is disabled, and a new weld is created with a suffix Cx (where x is the numbers of times the weld is rejected and reweld).

        For example, if a weld W01 is rejected during visual inspection and Reweld is selected as the reason for repair, a new weld is created with a suffix C1 and labeled as W01_C1 (where C1 indicates the first reweld).

    • Reason

      The Fit-up Internal Result and the Fit-up Client Result are set to Rejected on the weld. The Reject reason and inspection date are set in the appropriate fields on the weld.

      You can choose the accepted welds from various NDT (BSR) or PWHT or NDT (ASR) while creating an NOI or ROI. Rejected welds are not visible in NDT (BSR).

  23. Select the ROI and click Generate Report of Inspection . The software generates the report for the selected ROI.

  24. You can download, attach, and remove files for the welds. For more information, see Module Icons.