Define Project and Default Task Symbology Settings - Intergraph Smart Review - Help

Intergraph Smart Review Help

Language
English
Product
Intergraph Smart Review
Search by Category
Help
SmartPlant Foundation / SDx Version
7.1 (2018 R1)
Smart Review Version
13.x(2018)

Animation > ScheduleReview > Settings

To use this functionality, you must install the Construction module.

Displays the ScheduleReview Settings dialog box, which allows you to use abstract data from your project planning software to display the sequence of construction. You can also reverse the action, so that you can display the deconstruction sequence.

  1. Click Animation > ScheduleReview > Settings.

    You can also click Schedule Review Settings on the ScheduleReview toolbar.

  2. On the Project tab, choose a Project type.

    Project Tab (ScheduleReview Settings Dialog Box)

  3. Click Browse to select your Project file.

    Avoid opening a Microsoft Project planner file using automation through ScheduleReview (specifically, with the Refresh Active Project command) and concurrently opening the same file with an instance of the Microsoft Project application.

  4. Click Apply.

  5. When you have defined your project file, click the Symbology tab to define the default symbology of all tasks.

    Task Symbology Dialog Box

  6. Select a Type of task.

  7. Select Visibility for Default or Visible.

  8. Select Default for Style, or select Wireframe, Transparent, or Shaded.

  9. Select Default for Color, or select a specific color.

  10. Click OK to save your edits and close the dialog box.