Work Queue windows - Intergraph Smart Production - Help

Intergraph Smart Production Work Queue

Language
English
Product
Intergraph Smart Production
Search by Category
Help

You can open a work queue window for a work group, which can contain several work places, or for a work place. The name of the work group or work place displays in the header of the work queue window. The name of the active window displays in the header of the application.

If a queue for a work group is opened, the queue shows all the works assigned to the work places inside that group. This enables you to view the works of the whole work group in one list.

All work queue functions are not always available in the queue window of a work group.

The work queue window displays information about the cutting works. The order and variety of the information columns can vary according to the system configuration. The upper list in the window is the work queue of the work group or work place. It displays which works are assigned to a specific work group or place.

Order of the work queue

By default, the queue is ordered according to the due date of the works. That is, the work to be done first displays at the top of the list. The same queue order also applies for the workshop of the work place.

Work Queue window

Criteria selection

You can specify which works are shown in the list. Select the status of the work from the Criteria list below the work queue. The works that meet the selected are shown in the list.

Available options are listed below.

Work Queue

Displays works that are waiting to be done or are currently in progress.

Completed Works

displays works that are completed.

All

Displays both undone/ongoing and completed works.

Work Load

Shows the total work load of the selected work(s). On the right side, you can see how many rows are selected and how many rows are available.

Color indications

The software uses different color indications to show the status of the works.

Row color:

  • Green indicates that the work is completed.

  • Red indicates that the work is late for the set due date.

NC File cell color:

  • Green indicates that the work is active.

  • Yellow indicates that the work has been started but is currently not active.

  • Purple indicates that the work is put on hold.

Pick Lists cell color:

  • Yellow indicates that the work has been added to the Pick list, but the material has not been picked.

  • Green indicates that the work has been added to the Pick list, and the material has been picked.

Completion Date cell color:

  • Green indicates that the work was completed in time.

  • Red indicates that the work was completed late.

Remnant Cut Date cell color:

  • Green indicates that the remnant is available or used.

  • Yellow indicates that the remnant is being worked.

  • Red indicates that the remnant is unborn.

  • Purple indicates that the unborn remnant is scheduled earlier than the mother plate cut.

Tabs

After you select the tabs to display, additional information lists are visible below the work queue. These lists display extra information about the selected work.

Because additional information lists can show information on one work at a time only, make sure that only one work is selected when reviewing the extra information.