Additional work times related to panel process can be defined at the work place level. The Work Time Calculation tab is available in System Settings by selecting a work place in the tree view.

  • Work Instruction (Minutes / Nesting)

  • Nozzle Handling (Minutes / Nesting)

  • Material Handling (Minutes / Stock Material)

  • Scrap Removal (Minutes / Stock Material)

  • Manual Part Marking (Minutes / Part)

  • Part Picking Depending on Part Weight (Minutes / Part)

  • Nesting and Stock Material-related times are calculated only when nesting is available.

  • NC Time Factor has no effect on panel cutting calculation.