The following workflow demonstrates how to compare drawings in a connected Workshare collaboration using projects.
1 |
Project 1 checks out Drawing A. Project 1 assigns ownership of Drawing A to Satellite 1.1. |
2 |
Project 2 fetches Drawing A from Project 1. |
3 |
Project 2 assigns ownership of Drawing A to Satellite 2.1. |
4 |
Satellite 2.1 opens, claims items, and modifies Drawing A. Drawing A becomes Drawing A'. Satellite 2.1 exits Drawing A'. |
5 |
Satellite 2.1 assigns ownership of Drawing A' to Project 2. |
6 |
Satellite 1.1 opens, claims items, and modifies Drawing A. Drawing A becomes Drawing A''. Satellite 1.1 releases claims and exits Drawing A''. |
7 |
Satellite 1.1 assigns ownership of Drawing A'' to Project 1. |
8 |
Project 1 checks Drawing A'' into the Plant. |
9 |
Project 2 checks out Drawing A'' (without replacing Drawing A'). |
10 |
Project 2 compares Drawing A'' (modified in Project 1) with its own Drawing A'. |
11 |
Project 2 refreshes Drawing A' with differences from Drawing A''. Drawing A' becomes Drawing A'''. |
12 |
Project 2 checks Drawing A''' in to the Plant. |