  1. From the Home page, click Bill of Materials > Flat Configurations.

  2. To assign BOM procedures to the flat configurations, select the appropriate flat configuration and then click the Assigned BOM Procedures button to open the Assigned BOM Procedures select list.

  3. Click Add Row.

  4. Enter a unique number in the Seq cell.

  5. Select the appropriate procedure from the BOM Procedures select list in the Procedure cell.

  6. Select Pre or Post from the select list in the Execution cell to indicate whether the BOM procedure must be executed before (Pre) or after (Post) the OMI import.

    The Post procedures are not executed automatically during the import. If you run the import job with an enabled Pit Stop option, you must click the Run Procedures button.