Define a BOM rule - Intergraph Smart Materials - 10.2 - Help - Hexagon

Intergraph Smart Materials Web Help (10.2)

Language
English
Product
Intergraph Smart Materials
Subproduct
Web
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.2

Why do I need to define BOM Rules?

If you wish to administer assembly explosion and site activities on BOM idents or positions, then defining BOM Rules are necessary. BOM Rules can be divided into the following groups:

  • Module explosion for demand assessment Requisition

  • Module explosion for bills of materials BOM_Copy (physical copying)

  • Module explosion for assembly bill of materials Construction

  • Site Activities for assembly report Site Activity

It is also necessary to allocate a category must to the rule group. The categories are as follows:

  • Requisition

  • BOM_Copy

  • Construction

  • Site Activity

You can define any number of rules within the rule groups. A rule is defined by a name and a language-specific description. A Where condition must be allocated to rules with the Requisition, BOM_Copy, and Constructions categories. The Where condition for Site Activity is allocated only in the Activities block in the Rules and Activities page.

If a rule is in the Site Activities rule group, the relevant construction site activities like welding, piping, painting, insulation etc. must be defined. Property values and/or logic rules can be given in the where condition.

  1. On the Home page, click Bill of Materials, and then click BOM Rules.

  2. Click Add Row.

  3. Enter the group name in the Rule Group cell.

  4. Use the select list to select the appropriate Category.

    When you select Site Activity as the Category, the Activities block on the Rules and Activities page gets activated.

  5. Then add the descriptions in the Short Description and Description cells.