ZP_MFCTEXP - Intergraph Smart Materials - 10.2 - Help - Hexagon

Intergraph Smart Materials Web Help (10.2)

Language
English
Product
Intergraph Smart Materials
Subproduct
Web
Search by Category
Help
Smart Materials/Smart Reference Data Version
10.2

This project default specifies whether the expediter is responsible for assigning the manufacturer to a Change Order (CO) of a Purchase Order (PO).

Usually, the buyer assigns a manufacturer to the agreement (PO), but after agreement approval, the expediter can change the manufacturer, if this project default is set to Y.

  • Module(s) affected by this setting: Agreement > Agreements Overview > Agreement Details, Expediting > Item Shipment Details.

  • List of Values: Y and N (default).

    • If set to Y, and a change order is created for a PO, the expediter can assign a manufacturer to it.

    • If set to N, and a change order is created for a PO, then the manufacturer assigned by the buyer is carry forwarded and the expediter cannot assign a new one.