If all tasks related to an agreement are done, you can close the agreement. After
closing, the agreement is no longer available on the Expediting screen.
An agreement can only be closed, if all these conditions are met:
-
All supplements approved - all supplements of the agreement are approved.
-
All material received - all material ordered with this agreement is received on site. This means that the
ordered quantity (or more) of all item shipments has been received on site and has
been posted to the inventory. Depending on the setting of project default ZP_RCV_TOL,
the material is also regarded as being received if the complete quantity has not been
received on site. The value assigned to this project default represents a percentage
value. If the tolerance is 0 (zero, default value), the check box is only marked if
either all material or even more has been received and posted on site. If the tolerance
is greater than 0 (zero), this check box is also marked if less material has been
received. To what degree lower quantities are accepted depends on the value of the
tolerance.
-
All OS&Ds closed - all OS&Ds (Over, Short, and Damaged reports) created for this agreement are closed.
Additionally, for New Expediting (project default ZP_NEW_EXP set to Y):
Additionally, for Basic Expediting (project default ZP_NEW_EXP set to N):
-
All closeout activities checked - all closeout activities that have been assigned to this agreement are marked as
complete. This is, the Completed check box in the Closeout Activities tab on the Agreements screen must be selected for all assigned activities.
-
All NCRs closed - all NCRs (Non-conformance reports) are closed. Open NCRs means that item shipments
exist which are marked as inspectable, and at least one of these item shipments have
the NCR Date filled but not the NCR Release Date.
-
All supplements issued - all supplements of this agreement must have the Issued Date set.