Select Traffic from the Tasks list.
-
Click Shipments.
-
Click the shipment for which you want to create a pre-shipment.
-
Click the Pre-Shipments tab.
-
Click Create Pre-Shipment
.
-
(Optional) Select the existing pre-shipments that you want to be included in the new pre-shipment and click Next.
-
Select the packing lists that you want to include in the pre-shipment.
You can also expand a packing list and select specific packages to include in the pre-shipment.
-
Click Next.
-
Select the means of transport from the Means of Conveyance box.
-
The options that appear in the Means of Conveyance box, might vary depending on the packages selected in the step 5.
-
Depending on the means of conveyance selected, you might have to enter additional information on this page. For example, if you select Truck, you have to enter the truck number.
-
-
Click Next.
-
On the Schedule Shipping page, enter the estimated departure and arrival dates (ETD and ETA) for each destination.
The last row on the Schedule Shipping page is read-only.
-
Select the final unloading point and click Save.
-
You can enter the actual departure and arrival dates (ATD and ATA) when you know the actual dates.
-
When the pre-shipment needs to be collected from multiple locations, you can change the order of those locations by clicking the Move Up and Move Down arrows on the Schedule Shipping page.
-
You can enter specific details about a destination in the Precise Location box.
-
To delete a pre-shipment, select it and click Delete Pre-Shipment
. However, if the ATD of a pre-shipment is entered, it cannot be deleted. If the ATD is entered for the main shipment (at shipment level or truck/wagon level) then the corresponding pre-shipments cannot be deleted.
-