Click the shipment for which you want to create a post-shipment.
-
Click the Post-Shipments tab.
-
Click Create Post-Shipment
.
-
Select Link to Main Shipment, if you want the post shipment to pick packages from the main shipment. Otherwise, select Link to Existing Post Shipments and select the required post-shipments.
-
Click Next.
-
Select the packing lists that you want to include in the post-shipment.
You can also expand a packing list and select specific packages to include in the post-shipment.
-
Click Next.
-
Select the means of transport from the Means of Conveyance box.
-
The options that appear in the Means of Conveyance box, might vary depending on the packages selected in the step 5.
-
Depending on the means of conveyance (MOC) selected, you might have to enter additional information on this page. For example, if you select Truck, you have to enter the truck number.
-
-
Click Next.
-
If the post-shipment needs to deliver packages to more than one place, click Add Shipping Schedule
to add a row for each delivery designation.
You can click Delete Shipping Schedule
to delete a delivery designation.
-
Enter the estimated departure and arrival dates (ETD and ETA) for each destination.
-
You can enter the actual departure and arrival dates (ATD and ATA) when you know the actual dates.
-
When the post-shipment needs to reach multiple locations, you can change the order of those locations by clicking the Move Up and Move Down arrows. However, you cannot move the first and last rows which contain the starting point and the final destination of the post shipment.
-
You can enter specific details about a destination in the Precise Location box.
-
-
To delete a post-shipment, select it and click Delete Post-Shipment
. However, if the ATD of a post-shipment is entered, it cannot be deleted.