Select Traffic from the Tasks list.
-
Select Agreements from the list under Traffic Coordination.
-
Click the agreement number for which you want to rearrange the preliminary packages or item shipments.
-
On the Item Shipments tab, select the items that you want to rearrange.
-
Click
Rearrange.
-
Only the items editable by you are rearranged. The items that are being worked on by the supplier are not rearranged, even if they are selected.
-
The items belonging to a locked package are not rearranged even if they are selected.
-
If you select the items from the Not Packed Items section, then all the item shipments are automatically assigned to the matching PPLs.
-